Dropped Kerb Guide

How much does a dropped kerb cost?

Two costs: council fees (£132 to £568 in total across the 39 councils we've checked) and building the crossing (councils publish about £1,000 to £3,500 for a standard one). Pick your council for a sourced estimate.

Dropped kerb cost calculator

Not listed? Find your council.
From the kerb to your boundary. Lancashire's standard example uses 2 m.
Driveway surface
Anything in the way?

Choose your council to see its fee and an estimate.

The two parts of the cost

1. Council fees. The homeowner application fee runs from £50 (Leicester) to £568 (Devon) among the councils we've checked. Some councils add other fees, such as a second payment on approval or a licence or permit for your contractor (for example Leeds £345.90, West Sussex £309, Leicestershire £240, Essex £150, Nottinghamshire £80). Added together, total council fees run from £132 (Nottinghamshire) to £568 (Devon), counting councils that publish every fee and are taking applications.

2. Building the crossing. The kerbs are lowered, and the pavement from the kerb to your boundary is dug out and rebuilt strong enough for a car. Councils that publish prices put a standard crossing at roughly £1,000 to £3,500:

CouncilWho buildsWhat the council publishes
BCPCouncil or your contractorBCP gives a guide price of £2,000 for a standard crossover of 3 dropped kerbs and 2 tapers; each quote is priced individually.
BirminghamCouncil buildsPriced individually after inspection (size, materials, labour, traffic management, trees and street lighting), plus a £375 administration fee.
BradfordCouncil buildsBradford charges £1,995 plus VAT for a standard crossing and £1,596 plus VAT for an extension.
CoventryCouncil or your contractorIf approved, Coventry gives an estimated cost of construction, valid for three months.
DerbyCouncil or your contractorOption 2: Derby City Council gives a quote (valid six weeks) to build it.
DevonAny qualified contractorDevon says the work will probably cost somewhere between £1,500 and £3,000, more if obstructions or restrictions need moving.
HertfordshireCouncil buildsHertfordshire gives a quote for the full work after a successful assessment (its page has an estimate tool).
KentAny qualified contractorKent says contractors' prices can vary from £1,000 to £2,500.
Kingston upon ThamesCouncil buildsKingston says the maximum 4 m dropped kerb costs about £1,800; costs vary with the footway and materials.
LancashireCouncil's own list onlyLancashire says quotations are currently between £2,000 and £3,500 for a standard crossing (4.5 m wide at the kerb face, 2.5 m vehicle width, on a footpath normally 2 m wide).
LeedsAny qualified contractorLeeds says a standard crossing usually costs around £1,500.
LeicestershireCouncil or your contractorIf approved, Leicestershire's decision letter includes a quote for the work.
LincolnshireCouncil or your contractorIf the council builds it, Lincolnshire estimates construction at £2,500 to £3,500, priced on your property's needs.
ManchesterCouncil buildsManchester says the minimum new dropped kerb is roughly 3 m, with a starting cost of £1,575 including up to 2 m towards the property. Wider crossings, verges and obstructions cost more.
North YorkshireCouncil's own list onlyNorth Yorkshire can also quote to build it: a quote costs £102.36, and it says typical construction costs are around £2,000 plus a 10% admin fee.
Southend-on-SeaCouncil's own list onlySouthend's 2026/27 charge for building a domestic crossing is £255 per square metre.
SurreyCouncil's own list onlySurrey says building costs average roughly £1,800, depending on the work and the contractor.
ThurrockCouncil buildsThurrock's construction rate is £264 per square metre (2025/26 figure on its page), so an average standard crossing costs around £1,900.
West SussexAny qualified contractorWest Sussex's guidance says construction can vary between £1,000 and over £4,000, and moving streetlights or street furniture could be significantly over £2,000.

Dropped kerb fees by council: league table

Every row was checked on the council's own website on 3 October 2026. Select a column heading to sort. Fees aren't always like-for-like: some are partly refundable, Devon's licence is applied for by your contractor, and where councils build it themselves the fees are only the start of the price.

Dropped kerb council fees by council: homeowner application fee, other council fees and total council fees. Select a column heading to sort.
CouncilHomeowner application feeOther council fees (e.g. contractor licence/permit, where published)Total council feesWhat the fees cover / refundsWho buildsContractor requirementsValid forDecision timePublished build cost (not included in fees)SourceLast checked
Bradford£120None published£120Applications paused. Application fee: non-refundable if approved; £60 refunded if refused.Council buildsCouncil builds–28 working daysBradford charges £1,995 plus VAT for a standard crossing and £1,596 plus VAT for an extension.Council page3 October 2026
BCP£130Section 171 licence if you use your own contractor: amount not published£130 + an unpublished feeApplication and site inspection fee. Not refunded if you're refused, decide to use your own contractor, or don't go ahead. If BCP builds it: the £130 fee, then BCP's quote.Council or your contractorStreet works accredited; A Section 171 licence to work on the highway6 months (quote)–BCP gives a guide price of £2,000 for a standard crossover of 3 dropped kerbs and 2 tapers; each quote is priced individually.Council page3 October 2026
Nottinghamshire£52Contractor consent fee (paid by your contractor): £80£132Non-refundable charge for the initial assessment by Via (on behalf of the county council). Your contractor then pays £80 for consent to do the work.Any qualified contractor£5m public liability. A valid Streetworks qualification; At least £5 million public liability insurance6 months–Not publishedCouncil page3 October 2026
Hertfordshire£139None published£139Assessment fee to apply for a quote. Refundable within a 14-day cooling-off period, non-refundable after that.Council buildsCouncil builds–8 weeks (aim)Hertfordshire gives a quote for the full work after a successful assessment (its page has an estimate tool).Council page3 October 2026
Leicester£50Second payment if your application is approved: £100£150£50 non-refundable application fee, plus a second non-refundable £100 payment if approved.Any qualified contractorAccepted by Leicester City Council for your job before work begins6 months after contractor acceptance12 weeksNot publishedCouncil page3 October 2026
Derbyshire£160None published£160Non-refundable charge for inspection and administration, paid by you or your contractor within 7 days of the payment link.Any qualified contractor£5m public liability. Personnel qualified under the New Roads and Street Works Act accreditation scheme; At least £5 million public liability insurance3 monthsUp to 8 weeksNot publishedCouncil page3 October 2026
Southampton£165Road Opening Licence for your contractor: amount not published£165 + an unpublished feeNon-refundable fee (including VAT) for administration, assessment and a site visit.Any qualified contractor£10m public liability. New Roads and Street Works Act 1991 accreditation; £10 million public liability insurance–About 4 weeksNot publishedCouncil page3 October 2026
Nottingham£170None published£170Section 184 licence fee, after a pre-application enquiry.Any qualified contractorSuitably qualified (the council checks the details once you name them); Works need a valid Section 184 licence––Not publishedCouncil page3 October 2026
Derby£175
Option 1, with a private contractor
None published£175Non-refundable processing fee if you use a private contractor (Option 1). Option 2: Derby City Council quotes to build it.Council or your contractor£5m public liability. £5 million public liability insurance (copy with your application); Supervisors and operatives accredited on the Street Works Qualification Register––Option 2: Derby City Council gives a quote (valid six weeks) to build it.Council page3 October 2026
Kingston upon Thames£183.86None published£183.86Inspection fee, not refunded if the application is rejected (refundable to Blue Badge holders if refused).Council buildsCouncil builds3 years–Kingston says the maximum 4 m dropped kerb costs about £1,800; costs vary with the footway and materials.Council page3 October 2026
Edinburgh£210
Footway dropped crossing permit, per location
None published£210Footway dropped crossing permit, per location (2026/27). A 25% surcharge applies to applications made inside the 10-working-day minimum notice period.Any qualified contractorNRSWA accreditation certificate for the works supervisor; NRSWA accreditation certificates for the operatives–Minimum notice 10 working daysNot publishedCouncil page3 October 2026
Hampshire£211.90None published£211.90Non-refundable application fee. Optional Fast Track adds £97 (total £308.90) for a decision within two weeks. Optional Fast Track: +£97 for a decision within two weeks.Any qualified contractor£10m public liability. £10 million public liability insurance, indemnifying you and Hampshire County Council; Operatives and supervisors accredited under the New Roads and Street Works Act 1991 codes of practice12 months8 weeks (aim); 2 weeks Fast TrackNot publishedCouncil page3 October 2026
Sheffield£220None published£220Domestic application fee (light industrial £230). Online payment only.Any qualified contractor£2m public liability. Street Works qualifications; £2 million public liability insurance–About 10 weeksNot publishedCouncil page3 October 2026
Plymouth£104Conditional approval fee: £128; Section 171 highway permit for your contractor: amount not published£232 + an unpublished fee£104 application fee plus a £128 conditional approval fee if approved. Neither is refundable.Any qualified contractor£5m public liability. £5 million public liability insurance; Supervisor and operative accredited under NRSWA 1991–6 to 8 weeksNot publishedCouncil page3 October 2026
Oxfordshire£250
Residential access on an unclassified road
None published£250£250 for a residential access on an unclassified road; £400 on a classified road. Paid by BACS with the emailed application form. £400 on a classified (A, B or C) road.Any qualified contractor£10m public liability. Relevant Streetworks qualifications; £10 million public liability insurance12 months–Not publishedCouncil page3 October 2026
Coventry£200
With your own contractor
NRSWA permit (paid by your contractor): £75£275£130 if the council's contractor builds it (non-refundable). £200 if you use your own external contractor (£100 of it non-refundable). External contractors also need a £75 NRSWA permit. If Coventry's own contractor builds it: £130 application fee, then the council's estimate.Council or your contractor£5m public liability. Public liability insurance of at least £5,000,000; Supervisors' and operatives' NRSWA Streetworks qualification cards––If approved, Coventry gives an estimated cost of construction, valid for three months.Council page3 October 2026
Lancashire£290None published£290Paid when you apply. Half (£145) is refunded if the application is unsuccessful.Council's own list onlyMust be on Lancashire's approved contractor list (your own builder can apply to join); Works under a Section 171 licence, which is free when your approval code is used–28 days (aim)Lancashire says quotations are currently between £2,000 and £3,500 for a standard crossing (4.5 m wide at the kerb face, 2.5 m vehicle width, on a footpath normally 2 m wide).Council page3 October 2026
Southend-on-Sea£300None published£300Non-refundable application fee (£325 if the crossover crosses a watercourse or ditch). Construction is charged at £255 per m² for a domestic crossing.Council's own list onlySouthend's own authorised contractors only––Southend's 2026/27 charge for building a domestic crossing is £255 per square metre.Council page3 October 2026
Gloucestershire£105Part 2 fee (with the works certificate): £205£310Total, paid in two parts: £105 (non-refundable) with Part 1, then £205 with Part 2. Extra site visits £125 each. Fee in force from 1 April 2025.Any qualified contractor£5m public liability. Valid New Roads and Street Works accreditations; Public liability insurance of at least £5 million12 months–Not publishedCouncil page3 October 2026
North Yorkshire£310.20None published£310.20Domestic dropped kerb licence fee.Council's own list only£5m public liability. Must be on North Yorkshire's approved contractor list; Approved contractors hold £5 million public liability insurance and are on the Street Works Qualification Register––North Yorkshire can also quote to build it: a quote costs £102.36, and it says typical construction costs are around £2,000 plus a 10% admin fee.Council page3 October 2026
Bristol£357None published£357Combined excavation (Section 171) and vehicle crossover (Section 184) licence for a domestic crossover. A retrospective licence costs £536.Any qualified contractor£5m public liability. Public liability insurance of at least £5 million; All operatives NPORS or SWQR qualified under the New Roads and Street Works Act 1991––Not publishedCouncil page3 October 2026
Essex£210.18Road Opening Notice (paid by your contractor): £150£360.18Non-refundable initial application fee (covers the site visit, a search for underground apparatus and admin). If approved, your contractor pays £150 for the Road Opening Notice. Vehicle crossing fees carry no VAT.Any qualified contractor£10m public liability. Valid £10 million public liability insurance; All site workers NRSWA-accredited to Operative level, with at least one Supervisor-level person on site or available at any time6 monthsSeveral weeks after consentNot publishedCouncil page3 October 2026
Thurrock£375None published£375Paid upfront. £300 is returned if the application is refused; £150 is returned if it's approved and the crossing is built to standard.Council buildsCouncil builds––Thurrock's construction rate is £264 per square metre (2025/26 figure on its page), so an average standard crossing costs around £1,900.Council page3 October 2026
Surrey£383None published£383Non-refundable Stage 1 application fee. Covers the site assessment, marking out, utility searches, managing the works and the final inspection. A re-mark costs £116.Council's own list onlyMust be one of Surrey County Council's procured approved contractors6 months20 working daysSurrey says building costs average roughly £1,800, depending on the work and the contractor.Council page3 October 2026
Somerset£388.30None published£388.30Non-refundable fee for a Section 184 vehicle crossing licence (administration and site inspection).Any qualified contractorAccredited to work on the highway (Somerset's wording)3 months–Not publishedCouncil page3 October 2026
Leeds£55.06Section 171 licence (paid by your contractor): £345.90£400.96Non-refundable site inspection fee. Your contractor then pays £345.90 for a Section 171 licence.Any qualified contractorNRSWA accreditation; Section 171 licence (£345.90) before excavating––Leeds says a standard crossing usually costs around £1,500.Council page3 October 2026
Cambridgeshire£414None published£414Covers all inspection fees (no VAT). £314 is refunded if the application is unsuccessful.Any qualified contractorStreet works accredited–6 weeksNot publishedCouncil page3 October 2026
Cornwall£438None published£438Standard vehicle crossing licence. Licence fees are reviewed every year and new fees apply from 1 April.Any qualified contractor£5m public liability. Streetworks Supervisor and Operative qualifications; Public liability insurance of at least £5 million–At least 6 weeksNot publishedCouncil page3 October 2026
Suffolk£450None published£450Non-refundable application fee. Pre-application advice (for borderline cases) costs £225.Any qualified contractor£5m public liability. New Roads and Street Works Act 1991 qualified supervisors and operatives; Public liability insurance of at least £5,000,0001 year20 working daysNot publishedCouncil page3 October 2026
Lincolnshire£470
With a third-party contractor
None published£470£300 for a new light-duty application if the council builds it (removing an existing kerb: £125). £470 for a new domestic access if a third-party contractor builds it (£235 for extensions up to 2 m). If the council builds it: £300 application fee, then the council's price.Council or your contractor£10m public liability. Public liability insurance of at least £10 million; NRSWA accreditation for all operatives–10 working days (response)If the council builds it, Lincolnshire estimates construction at £2,500 to £3,500, priced on your property's needs.Council page3 October 2026
Birmingham£125Administration fee (included in the council's quote): £375£500Non-refundable application (inspection) fee on Birmingham's cost page (updated 1 April 2026). The quote also includes a £375 administration fee. Birmingham's older application page (updated 10 December 2025) still shows £113, so confirm the amount when you pay. Birmingham's older application page still shows a £113 application fee.Council buildsCouncil buildsApplication open 1 year after inspectionQuote within 28 working days of inspectionPriced individually after inspection (size, materials, labour, traffic management, trees and street lighting), plus a £375 administration fee.Council page3 October 2026
Kent£500None published£500Application fee. Extra inspections cost £76 each (for a new access point, or a dropped kerb near a tree or street light). £231 is refunded if the application is declined.Any qualified contractor£5m public liability. NRSWA accreditation for excavation and reinstatement; £5 million public liability insurance2 years28 days (aim)Kent says contractors' prices can vary from £1,000 to £2,500.Council page3 October 2026
Buckinghamshire£520.38None published£520.38Vehicular access licence fee.Any qualified contractor£10m public liability. £10 million public liability insurance; NRSWA accreditation (operative and supervisor cards, front and back)2 weeks (works window)Up to 28 daysNot publishedCouncil page3 October 2026
West Sussex£215Construction licence (your contractor applies): £309£524Non-refundable assessment fee. Your contractor then pays £309 for the construction licence.Any qualified contractorCompetent, insured and qualified (West Sussex's wording); Applies for the £309 construction licence6 months–West Sussex's guidance says construction can vary between £1,000 and over £4,000, and moving streetlights or street furniture could be significantly over £2,000.Council page3 October 2026
Leicestershire£300Permit fee (if you use your own contractor): £240£540Non-refundable application fee. If you use your own contractor, there's also a £240 permit fee. If the council builds it: the £300 fee, then its quote.Council or your contractor£10m public liability. £10 million public liability insurance; A current New Roads and Street Works accreditation card6 monthsAbout 6 weeksIf approved, Leicestershire's decision letter includes a quote for the work.Council page3 October 2026
Devon£568
Licence applied for by your contractor on your behalf
None published£568Licence fee. Your contractor applies for the licence on your behalf.Any qualified contractorApplies for the licence on your behalf––Devon says the work will probably cost somewhere between £1,500 and £3,000, more if obstructions or restrictions need moving.Council page3 October 2026
GlasgowSee Book of ChargesNone publishedNot publishedGlasgow says costs are in its Book of Charges, but the 2026/27 road permit and road traffic charge pages we checked don't list a footway crossing fee. Ask the council.Any qualified contractorA private civil engineering contractor, subject to the council's approval for the job––Not publishedCouncil page3 October 2026
ManchesterNo separate fee listedNone publishedNot publishedManchester's pages don't list a separate application fee. After assessment the council tells you the cost of the job, which you pay before it starts work.Council buildsCouncil builds90 days after approval and cost–Manchester says the minimum new dropped kerb is roughly 3 m, with a starting cost of £1,575 including up to 2 m towards the property. Wider crossings, verges and obstructions cost more.Council page3 October 2026
StaffordshireNot publishedNone publishedNot publishedStaffordshire's dropped kerb pages mention a non-refundable administration charge but don't publish the amount. It is shown when you apply.Any qualified contractor£5m public liability. Registered with Staffordshire's network and traffic management register; £5 million public liability insurance with no limit on the number of claims3 years2 to 3 weeks after inspectionNot publishedCouncil page3 October 2026

How to read the fee columns. Homeowner application fee is what you pay the council to apply. Other council fees are further fees the same council publishes for the job, such as a second payment on approval or the licence or permit your contractor needs (they usually pass it on to you). Total council fees adds them up. Where a council lets you use your own contractor, the figures are for that route; the other route is described in the notes. Construction prices aren't included. Where the council builds the crossing itself, you also pay its price for the work. "+ an unpublished fee" means the council says another licence or permit is needed but doesn't publish the amount. Every row links to the council page that shows the fee.

Two councils' figures couldn't be confirmed: Staffordshire doesn't publish its fee, and Glasgow's 2026/27 Book of Charges doesn't list one. Norfolk and Wiltshire aren't included because their websites blocked our checks.

What pushes the price up

Ways to keep the cost down

Questions people ask

How much is a dropped kerb on average?

Council-published prices for a standard crossing mostly fall between £1,500 and £2,500, plus council fees (a median application fee of £215 in our data, and £132 to £568 in total council fees). The full range runs from about £1,000 to £3,500, before extras like moving a lamp post.

Is the council fee refundable?

Usually not, though some councils refund part if you're refused: Kent £231, Lancashire £145, Cambridgeshire £314, Thurrock £300, Bradford £60.

Is VAT included?

Council fees are usually stated as the total you pay (Essex says its vehicle crossing fees carry no VAT; Southampton's £165 includes VAT). Bradford's construction price is £1,995 plus VAT.

Your next steps

Check your own council's rules first, then make sure your property qualifies before you apply.

Find your council Can I get a dropped kerb? Printable checklist